We spent a decent amount of time together last Friday, namely to go over the Schedule of Building Defects and to discuss some concerns we had with the construction to date.
Here's the outcome of the meeting:
1. concrete floor slab has been rectified and has been signed off by the engineer and relevant building surveyor.
2. corner of floor slab on right side of garage door opening has been rectified.
3. most of the engineering design issues that had been missed, have now been completed. Our SS was great in going through each issue listed and showing us how it had been rectified. There were a few Ankascrews (essentially, large screws that hold the DS and DSX studs (these are a special type of timber, usually found beneath lintels or at doors/windows) (they are marked on the engineering plan) [the engineers for our home are Buratt Consulting Engineers]) still missing, some Multigrip anchors (look like metal plates that help to secure the joining of timbers) still missing, hoop iron strapping still missing - and our SS confirms these will all be attended to.
4. the big concern in this section of the report was that the large steel beam that spans the entire width of our living room space and also supports the first floor is only screwed down to the lower wall top plates. This was flagged in the schedule (of defects), however, our SS confirms that the engineer is satisfied this is not a problem and has confirmed this in writing (by email).
5. untreated radiata pine framing nailed straight to the slab (ie direct ground contact) at the front of the garage. Again flagged in the schedule, but in the end, not replaced, our SS instead opting to place treated pine battens adjacent the existing timber uprights. We have been assured this is sufficient to prevent timber rot and the framing members failing prematurely.
6. the chipboard sheet flooring to first floor had not been fixed into the joists sufficiently. Our SS has confirmed the floor will actually be screwed down as part of the standard CG process.
We also asked our SS about the issues raised in the last post. He confirms the steel posts in the garage were measured short and therefore a small section was required to be welded to it to ensure the correct height. He assures us this is common place and that this in no way affects the integrity or strength of support and foundation in this area of the house.
The other areas we flagged ourselves with respect to the timber framing, such as the roof spanning beam that is seemingly only supported by 3 nails, and some entire timber frames (that will form walls in our house, namely rear garage/laundry and leisure) will also be rectified, with additional bracing and strengthening to be used.
We also noted that the silt pits that CG have installed around the house (4 in total) appear to be set very low. These pits need to be exposed and can not sit below the surface. We have requested that they are extended upwards.
All in all, a really solid meeting. We've lost a week or two along the way, but as long as mistakes are minimised and, if they do occur, are resolved and rectified to comply with the Australian Standards, we're happy. Certainly CG continue to be good builders to be working with.
Hi Hyatt38
ReplyDeletedid you have an external person point out these items for you? or are you a very educated/informed purchaser.
Cheers
Cathy, we had an external person check the build at frame stage. The frame report is the subject of a past post (try looking at our posts in Sept). We believe it was money well spent.
ReplyDelete